Investment activities
To ensure the stable growth of the country’s economy, the advanced development of the electric power industry as a whole, including the electric grid infrastructure, is necessary.
With a view to enhancing efficiency, increasing the reliability of the operation of the NPG and the throughput capacity of the grids, the Company is actively continuing the implementation of large-scale investment projects. These projects are implemented taking into account the creation of conditions for the development of RES (SPP and WPP, which are characterised by instability of generation) and the corresponding electric grid construction to ensure the feed-in of the capacity of large RES facilities.
In addition, the projects are of important social significance – during the period of construction and installation works (CIW), additional jobs will be created. This in turn will have a positive impact on the development of the real sector of the economy, the increase in employment and the well-being of the population, and the increase in tax contributions to budgets.
In 2025, the Company is implementing the following major investment projects:
KEGOC JSC Investment Projects in 2025
Integration of the energy system of Western Kazakhstan with the UPS of Kazakhstan. Construction of electric grid facilities.
Goal of the project
Construction of the 500 kV OHTL Karabatan SS – Ulke SS with a length of 604.3 km for the integration of the Western Zone with the main part of the UPS of Kazakhstan through the territory of the RK, in order to enhance the reliability of electricity supply to consumers of the Western Zone and to engage flexible generation of the Western Zone to offset imbalances in electricity and capacity
Source of funding
The project is financed from its own funds and from borrowings of the DBK and the EBRD.
Status of project implementation
Construction and installation works are under way on the project in accordance with the work schedule.
The completion date is
31 December 2027.
Strengthening of the electric grid of the Southern Zone of the UPS of the Republic of Kazakhstan.
Goal of the project
Strengthening of the electric power system of the Southern Zone of the UPS through the territory of the Republic of Kazakhstan to ensure the reliability of electricity supply to consumers of the Southern Zone and to strengthen the electrical connection between regions of the Southern Zone.
Source of funding
The project is financed from its own funds and from borrowings of the Asian Development Bank.
Status of project implementation
Construction and installation works are under way on the project in accordance with the work schedule.
The completion date is
30 June 2027.
In forming the portfolio of investment projects, KEGOC JSC uses a scenario approach based on the development and annual updating of the forecast balance of electricity and capacity of the UPS of the Republic of Kazakhstan. In addition, the risks of climate change are taken into account, namely natural factors (floods, hurricanes, earthquakes, epidemics) leading to the occurrence of the risk of an ES.
In order to ensure the reliability of the electric grid and to minimise the key risk of the occurrence of accidents and first-degree failures in the short term, the Company plans the implementation of the following investment projects aimed at the development of the NPG:
1. Reconstruction of 220–500 kV OHTLs of KEGOC JSC branches, Phase II.
The goal of the project is to enhance the reliability of the operation of the NPG of the Republic of Kazakhstan through the reconstruction of existing power lines that have reached their standard service life, as well as of OHTLs whose service life will reach the standard in the coming years.
The objects of reconstruction are 48 OHTLs of 220–500 kV on the balance sheet of the Akmola MES, Central MES, Eastern MES and Northern MES branches with a total length of 4,236 km. For the project, a feasibility study has been developed, a positive opinion of the RSE “Gosexpertiza” has been obtained, and the design and estimate documentation is being developed.
2. Reconstruction of 220–500 kV OHTLs of KEGOC JSC branches, Phase III.
The need for the reconstruction of the NPG is due to the following reasons:
- reaching and exceeding the design service life of a number of 220–500 kV OHTLs;
- enhancing the reliability of the electricity supply to consumers, the transit of electricity, and the feed-in of the capacity of power plants.
The objects of reconstruction are 44 OHTLs of 220–500 kV on the balance sheet of the Almaty MES, Central MES and Southern MES branches with a total length of 4,332 km. For the project, the state examination of the developed feasibility study is being carried out.
3. Strengthening of the external electricity supply scheme of Astana with the construction of a new digital 500 kV substation: the project is aimed at enhancing the reliability of the electricity supply of the capital, which will make it possible to cover the city’s growing needs for electricity and will also ensure the connection of new prospective consumers in the area of the city of Astana. For the project, the state examination of the developed feasibility study is being carried out.
4. Increasing the transit potential and throughput capacity of the UPS of Kazakhstan with the construction of the “North-South” direct current line: the project will make it possible to increase the throughput capacity of the North-South transit to 2,000 MW, as well as to effectively integrate the NPP and RES. The project will also address the tasks of covering the needs for electricity of the south of Kazakhstan, enhancing the resilience of the operation of the energy system in the context of the significant development of RES and the growth of loads.
In addition, in the long term until 2035, KEGOC JSC will consider supplementing the investment portfolio with the following major projects for the development of the NPG:
The project “Development of the electric grid of Almaty Region and Zhetysu Region”: the project will make it possible to ensure the connection of new consumers and will create the conditions and opportunities for the connection of new hydropower and RES facilities.
In order to strengthen regional energy cooperation and promote cross-border electricity trade between Azerbaijan, Kazakhstan and Uzbekistan, the project “Green Corridor” is planned for implementation, including the construction of a submarine cable line. The project provides for the integration of energy systems and the creation of a green corridor for the transmission and trade of renewable energy.
Also, the Company’s plans include the implementation of such projects as the construction of the Karaganda substation and a 500 kV OHTL from Astana to Karaganda. The goal of the project is to enhance the reliability of the electricity supply of the Central energy node, in which the country’s large industrial enterprises are concentrated.
To ensure the feed-in of the capacity of flexible power plants and large RES facilities, and to enhance the reliability of the energy system, the implementation of the project for the construction of the 500 kV OHTL Karaganda – Zhezkazgan – Kyzylorda – Shymkent is planned
.
In order to create the necessary conditions to ensure the feed-in of the capacity of the NPP and RES facilities, the implementation of the project to strengthen the Western energy node with the construction of 500 kV lines Karabatan SS – Beineu SS – Mangystau SS is also planned.
The project to integrate the Western Zone with the UPS of Kazakhstan (Phase 2) will make it possible to close the loop of Kazakhstan’s energy system and balance RES through the flexibility of the gas-fired generation of the Western Zone, and in the long term will create the conditions for the implementation of the Caucasus – Central Asia energy corridor.